The following information summarizes the status of
the construction projects currently underway in the
District through September 7, 2007.
Spring Forest Middle
School – Gym Replacement
Floor
A professional contract proposal has been received
from the architect and will be finalized in the following
week. Design, specifications, scope and drawings are
complete. An alternate/add is included in the scope
for bleachers due to their condition and the damage
they will cause the new floor. The proposal opening
will be September 20th, 2007. The contractor recommendation
to the Board of Trustees will be October 29, 2007
Bendwood School – Roof
Replacement and Remediation
This project is scheduled to be substantially complete
by October 16, 2007. The contractor currently
has completed 45% of the roof area. Work on the
North wing roof was scheduled to begin on September
3, 2007 but has been delayed due to weather conditions. The
SPIRAL area has been repainted and new flooring completed
on September 7, 2007, with move back on September 8,
2007 in time for new students on September 10, 2007. A
budget for the renovations necessary for the North wing
will be presented to the October Board.
Pine Shadows Elementary – Emergency
Plaster Soffit Removal
The restrooms are complete.
The metal replacement soffit is 65% complete and all
work should be completed by September 7, 2007.
Valley Oaks Elementary– Roof Replacement
The roofer is 99% complete. The punch list will
be created on Friday, September 7th.
The contractor is working on close-out documentation
at this time.
Athletics – New Dressing Facilities/Offices
Tully Stadium
The exterior concrete masonry unit (CMU) walls are
100% complete. The interior CMU walls are complete. The
concrete paving and the new 6”and 8” water
lines are complete. Split face block has started
and are currently at 15% complete. Roof fill was
completed the week of August 17th and roof installation
is at 20% complete. The substantial completion
date is December 15, 2007 with a final completion date
of
December 29, 2007.
Spring Branch ISD Police Command Center
The project continues to be on schedule. All
paving is now complete, with the exception of sidewalks. The
exterior face brick is approximately 98% complete along
with the glass block. The interior block walls
are complete and block fill painting is 75% complete.
Electrical rough-in is complete and drywall cover-up
is approximately 90% complete. Furniture and fixtures
from the Texas Department of Corrections is arriving
and being stored at the Maintenance Warehouse. SBISD
Police alarm technicians have completed the installation
of both the CCTV and security wiring.
The phone system has been approved by Technology Services
and has been ordered by the general contractor.
Work on the old police building began the week of August
20 2007. The contractor is going to install oil
field mats so that they can gain better access.
Spark Park No. 17 -Meadow
Wood Elementary
The frame work for the new pavilion has been installed
and the entry portals are ready for finishing. Work
on the concrete seating and sundial has been delayed
due to weather. The project is scheduled to be
completed prior to the City wide dedication of all SPARK
parks in November.
Spring Branch Education Center -
Chiller Replacement Project
This project is substantially complete, waiting on
final closeout documents.
Natatorium – Roof Replacement
A notice to proceed was issued on July 3, 2007 and
a pre-construction meeting was held on July 9, 2007. A
meeting with Athletics is scheduled for September 11,
2007. The contractor is to begin as soon as all
issues with Athletics are addressed.
Don Coleman Coliseum – Roof Replacement
A preconstruction meeting was held the week of August
27th.
A preconstruction meeting with Athletics will be scheduled
in mid September.
Spring Branch Education Center – Roof
Replacement of Single Ply Areas
These areas are the Support Center, Competition Gym
and Practice Gym.
A preconstruction meeting was held the week of August
27th and work should begin the week of September 3rd.
Work as scheduled has been delayed due to weather conditions.
|