Summary of Proposed work

This project consists of mechanical/HVAC system upgrades and site improvements, including new courtyard lighting. In addition, they will receive new classroom furniture and technology student devices. 

Built in 2001, Bear Blvd houses pre-k and childcare rooms. The building consists of 26,000 square feet, with a student enrollment of 313. 

Scope of Work
  • Replace chillers
  • Install LED lighting in courtyard  
 
Project Status

Construction stage


Construction questions

All other inquiries

Architects, Contractors & Timelines

  • Architect: Johnston LLC
  • Contractor: Bass Construction
  • Timeline (Calendar Year)
Begin Design Begin Construction Scheduled Completion
2Q 2018 1Q 2019 3Q 2019

 