Summary of Proposed work

This project will consist of building system upgrades including: exterior/interior upgrades, site improvements, and a partial roof replacement. In addition, the campus will receive new classroom furniture, technology student devices, and athletic upgrades (i.e. track and tennis/sport court resurfacing, and field refurbishing). 

Spring Oaks Middle opened its doors in 1967, and consists of 189,660 square feet with a 2017-2018 student enrollment of 735. 

Scope of Work

Renovation of 2,800 sf of administration and clinic area to provide visibility to the front entrance of the campus. 34,600 sf of roof replacement and the windows replacement for the New Gym. Fire alarm, security alarm and access control improvements. Adding supplemental lighting to classrooms, building and LED site lighting upgrades. 


Project Status

Complete


Bond questions

Communications questions

Architects, Contractors & Timelines

  • Architect: Pfluger
  • Contractor: Bass Construction
  • District Project Manager: Noel Moreno
  • Timeline (Calendar Year)
Begin Design Begin Construction Scheduled Construction
2Q 2018 2Q 2019 2Q 2020

 


 

Bond Plan 2017


Monthly Project Reports


Project Advisory Team Charge


Project Advisory Team Roster


Project Advisory Team Meeting Schedule


Project Advisory Team Minutes


Board Updates

Downloads

Campus Bond Info Sheet

FAQs

Photo Archive

Project Videos