Summary of work
This project consists of mechanical/HVAC system upgrades and site improvements, including new courtyard lighting. In addition, they will receive new classroom furniture and technology student devices.
Built in 2002, Wildcat Way houses pre-k and childcare rooms. The building consists of 26,000 square feet, with a 2017-2018 student enrollment of 284.
Scope of Work
- Replace chillers
- Install LED lighting in courtyard
Project Status
Phase Bidding
Architects, Contractors & Timelines
- Architect: Johnston LLC
- Contractor: TBD
- District Project Manager: Kris Drosche
- Timeline (Calendar Year)
Begin
Design
|
Begin
Construction
|
Scheduled
Completion
|
2Q 2018 | 1Q 2020 | 3Q 2020 |