Woodview Elementary

Bond 2017

Summary of Proposed work

The project will replace the existing Woodview Elementary.

 

Since opening its doors in 1958, Woodview Elementary has received several additions. The campus consists of 70,508 square feet with a 2019-2020 student enrollment of 586. 

Scope of Work

The existing Woodview Elementary will be demolished and replaced with a new building.

Project Status

Planning

  • Architect: Stantec
  • Contractor: Brookstone
  • District Project Managers: David Ramirez

Bond Plan 2017


Project Advisory Team Charge


Project Advisory Team Roster


Project Advisory Team Meeting Schedule


Project Advisory Team Presentations

01/18/22 | 02/08/22 | 03/08/22 | 04/05/22 | 04/26/22 | 05/16/22


Board Updates

2022
6/30/2022 | 7/31/22 | 9/30/22 | 10/31/22 | 11/30/22 | 12/31/22
2023
1/31/23 | 2/28/23 | 3/31/23 4/30/23 | 05/31/23 | 06/30/23 | 07/31/23 | 08/31/23 | 09/30/23 | 10/31/23 | 11/30/23 | 12/31/23
2024
03/31/24 | 04/30/24 | 05/31/24 | 06/30/24 | 07/31/24 | 08/31/24 | 09/30/24