During the district’s summer months, scheduled bond projects continue at many schools and facilities. The summer closure and the absence of students and staff due to COVID-19 restrictions has led Spring Branch ISD to be able to move ahead with few disruptions. Construction-related work is deemed an essential service.

In November 2017, Spring Branch residents voted by an 80 percent margin for a $898.4 million bond issue to continue rebuilding and renovating school facilities and to provide districtwide improvements to all SBISD campuses.

Summer updates to major projects include (but are not limited to):

Memorial High School

o   New tennis courts and a new tennis field house are visible on the school’s east campus, and underground utilities to the new tennis fieldhouse and court lighting are complete. Final checks pending.

o   Building pads and underground plumbing for new Cafeteria and Classroom Building are complete; work will proceed on this four-story building for a long period.

o   Work progresses on fencing and gates, underground detention, and hall painting and renovations on existing building and wings.

Northbrook High School

o   Site logistics and city permits are being finalized after Board plan approval; project construction fencing will begin soon.

Spring Woods High School

o   Work is ongoing on HVAC (heating, ventilation, air conditioning) and fire alarm systems, and complete on the Gessner sidewalk.

o   Newly rebuilt cafeteria finishing work proceeds, while work planned on extensive library renovations begins with demolition; classrooms impacted will be reassembled for reopening.

Stratford High School

o   Demolition of the existing fine arts auditorium will occur after site logistics and city permits are finalized.

High school turf fields

o   Both Memorial and Spring Woods high school turf fields are now essentially completed; final approvals for athletics use is pending. 

 

Pre-K Centers: Tiger Trail and Wildcat Way Schools for Early Learning

o   Temporary chillers installed while existing chillers removed; HVAC and other mechanical and electrical upgrades in progress; all work remains on schedule.

 

Elementary school renovations, upgrades and additions

o   Buffalo Creek and Treasure Forest – Similar renovation/update plans at these campuses remain on schedule. Updates include teaching walls with projectors; library renovation with skylight installation for natural light; restroom upgrades plus other interior and exterior renovations; roofing replacement work continues.

o   Cedar Brook – Work continues on construction of new classroom addition to include six classrooms, two music rooms and one science classroom and lab; existing renovations include teaching walls with projectors; library renovation with skylight installation; restroom upgrades, and new metal roofing installation.

o   Hunters Creek – After earlier site demolition, steel framing for the new school gym and cafeteria have begun on complete rebuilding planned for this elementary school.

 

Middle school highlights

o   Landrum Middle – New building foundation laid; steel framing has begun on this multi-story building, the first middle school slated to be rebuilt in the district.

o   Spring Forest Middle – Roof replacement continues, with reception area renovation including secure vestibule near completion; a chain link, plus gate and decorative fencing will be also be installed.

To view Bond 2017 planning updates in detail and the Bond Oversight Committee presentation (May 27, 2020), please visit the Bond 2017 website.